Amtrak begins construction for new concrete platform at Toccoa Train Depot
Passersby may have noticed the construction trailer that was moved into the parking lot of the Toccoa Train Depot late last week.
According to Toccoa’s Community Development Director Connie Tabor, Amtrak will construct a new concrete 800-foot platform in compliance with ADA requirements and install 20 period appropriate lights along the Toccoa Depot Platform.
Mobilization for the proposed construction project began last week.
Tabor says the project timeline will be a 10-month construction period and is funded by Amtrak.
The new platform will meet Norfolk Southern requirements’ consisting of 8-inches of concrete, 12-feet in width, and 800-feet in length.
Centennial Contractors Enterprises is the General Contractor for the construction.
In a press release issued last week, Amtrak will work with Norfolk Southern Railway throughout the construction period.
Tabor notes that the depot parking lot along with a portion of Foreacre Street will be used to store materials and equipment.
The project will also include demolition of the existing platform, new signage and lighting, egress ramps, a wheelchair lift enclosure along the platform, regrading and repaving the Amtrak parking lot, addressing storm drainage, and removal and replacement of some existing shrubs, rose bushes, landscape timbers, and a crape myrtle.
According to Tabor, the platform area will be made available for passenger use during the hours of passenger train operations.
All work will be performed behind a temporary construction fence.
Last week, perimeter fencing was installed for the job trailer and laydown area in the depot parking lot, north of the station.
The project will be completed in four phases with each phase being completed before the construction moves to the next phase.
For additional information regarding the project contact Tabor at 706-282-3269.
WNEG News will continue to follow this story and bring you additional details as they become available.